Post by ALEngineer »

PL-N5 cable protectors.

Assembly of PL-N5 and PL-G5 cable protectors from Bugulma Electric Pump Plant (BENZ) from BENZ (Bugulma Electric Pump Plant) on ESP pump-section connections.

1. Install the cable protector after the ESP pump-section flange is joined and the studs are torqued.

2. Remove the protective ribs from the ESP pump-section base.

3. Lay the Motor Lead Extension (MLE) in the groove of the cable-protector body, install the cable protector in place of the protective ribs, and tighten the bolted joint (tightening torque 3.0 kgf*m).

Appearance of a BENZ PL-N5 cable protector.
pln5.jpg
Original topic (RU)
Инструкция по монтажу протектолайзеров ПЛ-Н5 производства ОАО "БЭНЗ" на соединение секций ЭЦН.

- Установку протектолайзера производить после сочленения и протяжки шпилек фланцевого соединения секций ЭЦН;
- Удалить защитные ребра с основания секции ЭЦН;
- Уложить кабельный удлинитель в паз корпуса протектолайзера, установить протектолайзер вместо защитных ребер, затянуть болтовое соединение (момент затяжки 3,0 кгс*м).
pln5.jpg
Внешний вид протектолайзера ПЛ-Н5 производства ОАО БЭНЗ