ESP well ramp-up instruction

Field and shop procedures for ESP installation, pull, commissioning, and related work instructions, including operator ETT (Unified Technical Requirements).
ALEngineer
Site Admin
User avatar
Posts: 579
Joined: Wed Mar 18, 2026 2:51 pm

ESP well ramp-up instruction

Post by ALEngineer »

The aim of ramp-up (bringing an ESP well to stable operating mode) is to keep the ESP alive in the first period after workover when the well is put on production.

The main task is not to overheat the ESP motor and the Motor Lead Extension (MLE), and to trip the ESP if the dynamic level falls to the critical value, allowing for well cleanup. To that end, every 15 minutes after start, watch rate and how fast the dynamic level is falling. Do not pump the dynamic level below 300-400 m above pump intake, or below 25-30 atm intake pressure if the ESP has an intake-pressure sensor.

Instruction, ramp-up memo, and process pack are attached.
ESP ramp-up instruction.rar
ESP ramp-up memo.zip
ESP ramp-up process.zip
Original topic
Целью операции по выводу скважины с УЭЦН на режим является обеспечение работоспособности УЭЦН в начальный период ввода скважины в эксплуатацию после ремонта.
Основная задача состоит в недопущении перегрева ПЭД, удлините-ля кабеля и обеспечении отключения УЭЦН при снижении динамического уровня до критического значения с учетом освоения скважины. С этой целью, с интервалом 15 минут, после запуска УЭЦН осуществляется регулярный контроль за величиной подачи из скважины и темпом снижения динамического уровня. Не допускается откачка динамического уровня ниже 300-400 метров над приемом насоса или ниже даdления 25-30 Атм. на приеме насоса (в том случае если УЭЦН оборудован датчиком давления).
Инструкция:
Памятка по ВНР:
Тех.Процесс:
ESP ramp-up instruction.rar
ESP ramp-up memo.zip
ESP ramp-up process.zip